Downtime cost calculator: what does machine downtime cost you?
Every minute a machine stands still comes back as lost output, idle labor and repair costs. Enter how long the stop lasted, the machine's output rate and the costs involved, and the calculator works out the cost of downtime per stop, per minute and per year. Below it you will find why each cost goes in and the most common mistakes.
Last updated: 30 October 2026
Downtime cost calculator
The fields start with the example further down. Type in your own numbers. If the same kind of stop happens several times a month, enter that in the last field to see the yearly figure.
Downtime cost calculator
Enter how long a stop lasted, the machine's output rate and the costs involved to get the cost of the downtime as you type.
90 / 60 × 40
60 × $3.50
1.50 × 2 × $25.00
$885.00 / 90
$885.00 × 4 × 12
The calculator runs in your browser. Nothing you type is sent anywhere or saved. Amounts are shown in dollars, but any currency works as long as you use the same one throughout.
What goes into the cost of downtime?
| Cost | How to calculate it | Note |
|---|---|---|
| Lost contribution margin | Lost pieces × (price − variable cost) | Only a real loss if the output cannot be made up later. |
| Idle labor | Downtime × people waiting × hourly cost | Smaller if operators can switch to other work. |
| Repair and spare parts | Service, parts, maintenance team time | Usually zero for stops that are not breakdowns, such as waiting for material or setups. |
| Catch-up cost | Overtime or subcontracting to recover the lost output | Use this instead of lost margin, not as well as it. |
| Scrap and restart | Scrap from the first parts after the stop | Large in injection molding and stamping. |
| Late penalties | Contract penalties or a lost order | Not every stop, but the biggest cost when it happens. |
The calculator has separate fields for the first three. Add overtime, scrap or penalties to the repair and other costs field.
Why contribution margin and not the selling price?
When a machine stops, no material is used and less energy is spent. What you lose is not the full selling price of the part but the contribution margin, the price minus variable costs. A calculation based on the selling price makes downtime look several times more expensive than it is, and people stop believing it.
The second question is whether the output is really lost. A stop on a machine that would have been idle anyway does not reduce output, the job simply runs the next day. On the bottleneck machine that the whole shop waits on, every minute is lost for good. Calculate downtime cost for bottleneck machines first.
Downtime cost example
An injection molding machine makes 40 parts an hour. A hydraulic fault stops it for 90 minutes. The contribution margin is $3.50 a part. Two people wait during the stop at $25 an hour each. Service and parts come to $600. A stop like this happens four times a month. The numbers are an example, so use your own.
| Item | Calculation | Result |
|---|---|---|
| Lost output | 90 ÷ 60 × 40 | 60 pcs |
| Lost contribution margin | 60 × $3.50 | $210.00 |
| Idle labor | 1.5 × 2 × $25 | $75.00 |
| Repair and other | $600.00 | |
| Cost of this stop | $885.00 | |
| Cost per minute | $885 ÷ 90 | $9.83 |
| Cost per year | $885 × 4 × 12 | $42,480.00 |
One stop looks small. Four a month add up to more than $42,000 a year, which is a useful number to have when deciding whether preventive maintenance or a spare parts stock is worth it.
Common mistakes
- Using the selling price. The cost comes out inflated and nobody takes it seriously.
- Applying one machine's cost per minute to every machine. Downtime on a machine that is not a bottleneck is often only labor and repair.
- Ignoring short stops. Nobody writes down a five-minute stop, but over a day they can add up to more than the longest breakdown.
- Counting only breakdowns. Waiting for material, no operator and long setups are downtime too, and in many shops they take more time than breakdowns.
- Counting the loss and the catch-up. If the lost output was made up with overtime, use the overtime cost instead of the lost margin.
Getting the downtime right
A downtime cost is only as good as the downtime that goes into it. Times written down from memory at the end of the day miss the short stops and round off the long ones. The machine downtime tracking guide covers how to sort stops by reason and where to start.
ModernMES records a stop when it happens. Operators pick a reason when they pause a job on the terminal or their phone, and the stop closes with its duration when the job resumes. Reasons and their categories are edited in the settings. The panel raises an alert when a machine has been stopped for more than 5 minutes and when a stop has gone unexplained for 10 minutes, and both times can be changed. ModernMES does not put a cost on downtime. You can turn the recorded times into cost with this calculator.
Frequently asked questions
How do you calculate the cost of downtime?
Multiply the pieces lost during the stop by the contribution margin per piece, then add idle labor and repair costs. With the example's numbers, a 90-minute stop on a machine that makes 40 parts an hour costs $885.
How do you work out the cost of downtime per minute?
Divide the total cost of a stop by its length. In the example, $885 ÷ 90 minutes is $9.83 a minute. The figure varies from machine to machine and is usually highest on the bottleneck.
Should planned downtime be included?
Breaks and planned maintenance are part of the plan and are not losses. Use the calculator for unplanned stops. Setup time is a loss that can be reduced, so it is worth costing as well.
Is anything I type into the calculator saved?
No. The calculation happens entirely in your browser. The numbers are not sent to a server and are gone when you close the page.
Related pages
- Machine Downtime Tracking: Downtime Reasons and AnalysisHow to track machine downtime: a short list of downtime reasons, paper vs Excel vs software, Pareto analysis, MTTR and MTBF, and common mistakes.
- Downtime Tracking Template for Excel (Free)Free machine downtime tracking template. Log when a machine stopped and why, and get minutes, groups and a Pareto by reason from the built-in formulas.
- OEE Calculator: Calculate OEE With a Worked ExampleFree OEE calculator. Enter planned time, downtime, ideal cycle time and counts and get OEE as you type, with a worked example, the formula and common mistakes.
- Takt Time Calculator: Takt Time vs Cycle TimeFree takt time calculator. Get takt time from available time and demand, compare it with cycle time and see whether you can meet demand. Takt vs cycle vs lead time, with an example.