Takt time calculator: takt time vs cycle time
Takt time is how often a part has to come off the line to keep up with customer demand. Cycle time is how long the machine or station actually takes per part. Enter your working time, demand and cycle time below to get takt time and see whether you can meet demand.
Last updated: 30 October 2026
Takt time calculator
The fields start with the example further down. Type in the numbers for your own line or machine and the result updates on the right.
Takt time calculator
Enter the daily working time and demand to get takt time. Add the cycle time to see whether demand can be met.
1 × (480 − 30)
450 × 60 / 600
450 × 60 / 52.0
52.0 / 45.0
1.16, rounded up
Cycle time is longer than takt time. At this cycle you fall 81 pieces short each day.
The calculator runs in your browser. Nothing you type is sent anywhere or saved.
What is takt time and how do you calculate it?
Takt is German for beat or pulse. Takt time is the pace production has to keep to match customer demand. It has nothing to do with the machine and comes from just two numbers.
Takt time = Available working time ÷ Customer demand
Available time is the shift minus breaks, lunch and scheduled meetings. Demand has to cover the same period. If you use daily time, use daily demand, and weekly demand with weekly time.
What is cycle time?
Cycle time is how long a machine or station takes to finish one part and move on to the next, including loading, processing and unloading. Measure it as the average over several parts. If one cycle makes several parts, as on a 4-cavity mold, divide the cycle by the number of parts.
The ideal cycle time used in OEE is something else. It is the fastest the machine can make the part. The gap between actual and ideal cycle time shows up in OEE as performance loss.
Takt time vs cycle time vs lead time
| Takt time | Cycle time | Lead time | |
|---|---|---|---|
| What it tells you | How long each part may take, given demand | How long each part actually takes on the machine | Time from order to delivery |
| Depends on | Working time and demand | Machine, tooling, method, operator | Every operation, queue and wait |
| Unit | seconds per piece | seconds per piece | days or hours |
| Who changes it | Demand and the shift pattern | Engineering and the shop floor | Planning, flow and queue management |
The rule is simple. If cycle time is shorter than takt time, you meet demand. If it is longer, you fall further behind every day. Lead time is far longer than cycle time because it includes all the time a part spends waiting.
Takt time example
A line runs one shift of 480 minutes with 30 minutes of breaks. The customer wants 600 parts a day. The cycle time at the line's bottleneck station is 52 seconds.
| Item | Calculation | Result |
|---|---|---|
| Available time | 480 − 30 | 450 min |
| Takt time | 450 × 60 ÷ 600 | 45.0 s |
| Pieces per day | 450 × 60 ÷ 52 | 519 pcs |
| Cycle / takt | 52 ÷ 45 | 115.6% |
| Parallel machines needed | 1.16, rounded up | 2 |
Cycle time is 7 seconds longer than takt time, so the line falls 81 parts short every day. With a second shift, available time goes up to 900 minutes, takt time to 90 seconds, and the same machine can make 1,038 parts a day. Set shifts to 2 in the calculator to see it.
What to do when cycle time is longer than takt time
- Add working time. Add a shift, or stagger breaks so the machine keeps running.
- Add a parallel machine at the bottleneck, or move part of the work to another machine.
- Balance the line. Move some of the work from the long station to the shorter ones.
- Shorten the cycle. Toolpaths, cutting parameters, fixturing and part handling are the first places to look.
- Cut lost time. Setups and short stops eat into available time, and every minute lost at the bottleneck comes off daily output.
A cycle time far below takt time is a signal too. The machine or the operator is idle for part of the day. One operator running two machines, or merging stations, may be worth a look.
Is takt time useful in a job shop?
Takt time was designed for repetitive production where the same part runs all day. In a CNC job shop that runs a different part every day, a single takt time means little. More useful there is knowing the planned and actual cycle time of each operation and comparing the weekly workload with capacity.
Cycle time itself matters in every shop, because quotes, capacity and OEE all depend on it. ModernMES records the actual time of each operation when the operator starts and finishes it on the terminal. The typical time of each operation is recalculated every night from past jobs, so planned times can be corrected against reality. ModernMES does not calculate takt time.
Frequently asked questions
How do you calculate takt time?
Divide available working time by customer demand. A line with 450 minutes a day and demand of 600 parts has a takt time of 450 × 60 ÷ 600 = 45 seconds.
What is the difference between takt time and cycle time?
Takt time is how long each part may take given demand, and it does not depend on the machine. Cycle time is how long the machine actually takes per part. Cycle time has to be shorter than takt time.
How do you measure cycle time?
Measure the time from one part being finished to the next part being finished. Take the average over several parts rather than one reading, and keep setup time out of it.
Are breaks included in takt time?
No. Available time is the shift minus breaks and planned stops. Unplanned stops are not taken off. They are the losses that make it harder for cycle time to keep up with takt.
Is anything I type into the calculator saved?
No. The calculation happens entirely in your browser. The numbers are not sent to a server and are gone when you close the page.
Related pages
- OEE Calculator: Calculate OEE With a Worked ExampleFree OEE calculator. Enter planned time, downtime, ideal cycle time and counts and get OEE as you type, with a worked example, the formula and common mistakes.
- Downtime Cost Calculator: What Machine Downtime Costs YouFree downtime cost calculator. Work out what a machine stop costs per minute and per year from lost output, contribution margin, idle labor and repair costs, with an example.
- How to Calculate OEE: OEE Formula and Calculation ExampleThe OEE formula (availability × performance × quality), a step-by-step worked example on a CNC lathe, the six big losses, common mistakes and a free calculator.
- Production Tracking Spreadsheet: Free Excel TemplateFree production tracking spreadsheet for Excel. Log machine, operator, work order, time, good and scrap counts. Scrap rate and machine totals are built in.