Hour-by-hour production tracking for series production

In a plant that makes the same product in volume, the question is not where an order is but whether this hour is on target. The ModernMES series production module shows the quantity made against the target for every machine, hour by hour, pulls the reason for a lost hour from the stop records, and measures the time lost in product changeovers.

Last updated: 21 November 2026

Why tracking is different in series production

In a make-to-order shop every job is different and what you follow is the stage of the job. In series production the product stays the same for months and what changes is the rate. A shift leader looks for answers to these questions during the day:

  • Are we ahead of target or behind right now, and by how many pieces?
  • Which machine fell behind, and in which hour?
  • What happened in that hour, and why did the machine stop?
  • How long did the changeover take, and is it better than last week?

When the answers sit on a sheet filled in at the end of the shift, or in numbers typed into a spreadsheet the next day, the loss is noticed too late to do anything about it. Hourly tracking makes the gap visible inside the same shift.

The hour-by-hour board

One sentence sits at the top of the screen: how many pieces you are ahead of or behind target. Below it there is a card for every machine with the quantity made, the target, the difference and the time stopped that day. The status is written in words as well as colour, so "42 behind" reads the same to someone who cannot tell red from green.

  • Hour-by-hour table: each cell holds the quantity made and the target of that hour. An hour that reaches 95% of its target is green, between 80% and 95% amber, below that red.
  • Running total: the same table added up from the start of the day. It shows how the gap grew or closed.
  • Line totals: machines are grouped by resource group, with a total per group and for the whole plant.
  • Big screen: the machine cards open full screen on a television on the shop floor and refresh by themselves.
  • Shift: with the Shifts module on, you look at the hours of one shift only.
  • End of shift forecast: while a chosen shift is running, the board says how many pieces ahead of or behind target you end the shift at the pace so far.
  • Colour limits: the green and amber limits can be changed in production settings to suit your own workshop.

Where the target comes from

A board with a target nobody believes is of no use. Dividing the daily quantity by eight, or giving every product one average rate, gives the wrong answer. ModernMES works the target out from the job running on the machine:

  • The work order quantity and estimated time give that product's hourly rate. Without an estimated time, the hourly target you set on the machine is used.
  • When the product changes within an hour, each product counts at its own rate for the time it ran.
  • The target does not run through the breaks of the shift you choose.
  • A machine with no job has no target. Pauses longer than eight hours and open jobs nobody has touched for a day do not build up a target.

While a job is on the machine the target keeps running through stops. If the machine stood for half an hour, that hour ends below target and the question of why becomes visible. To turn a cycle time into pieces per hour, see the takt time calculator.

The reason behind a lost hour

A red cell changes nothing by itself. What matters is what happened in that hour. The "Hours that fell behind" list under the board shows every hour that ended below 80% of its target, with how many pieces were short and the reason of the stop recorded in that hour.

Nobody types the reason a second time, because it is already on record. The operator picks the stop reason on the terminal when pausing a job, and a machine that sends signals opens the stop by itself. Stops with no reason are marked in the list, so it is clear what still has to be filled in. How stops are classified is covered in the machine downtime tracking guide.

Product changeover times

Changeover, also called setup or die change, is one of the places where series production loses most time, and in many plants it is only a stop reason on a list. ModernMES lists every changeover as a record of its own. It asks for no extra entry: it measures the time between the end of a job and the start of a job for a different product on the same machine.

  • From which product to which: every product pair has its own line. Going from A to B does not take the same time as going from B to A.
  • Typical and best time: the typical time is the median, which one bad day does not move the way it moves an average. The best time shows how short that changeover can be. The gap between the two is the time there is to win.
  • Week by week: whether the typical changeover is getting shorter.
  • By machine: which machine loses most time in changeovers.

A changeover can also be started with the button on the machine card. The clock counts against the target time you set on the machine, shows the time left and turns red once the target is passed. It stops by itself when the next job is started on the machine. Changeovers measured this way are marked in the report, which also shows how many kept their target time.

Lean sources define changeover time as last good part to first good part of the new product. ModernMES measures it from the job records, from finishing one job to starting the next. Consecutive jobs for the same product and gaps longer than eight hours (nights, weekends) are not counted.

How the counts reach the board

There are two ways, and they can be used together.

  • Operator terminal: the operator starts, pauses and finishes the job on a tablet or phone and enters the quantity when finishing. That quantity is spread over the minutes the job ran.
  • Automatic count from the machine: when a machine or a counter sends signals, each cycle lands in the hour it was counted. Where one cycle makes several parts, as with a multi-cavity mold, you set a multiplier. Machines can be read over OPC UA, Modbus TCP, Siemens S7, MTConnect and MQTT.

On a line that makes tens of thousands of pieces a day, seeing the real number hour by hour takes automatic counting. A quantity entered by hand reaches the board when the job is finished.

Whiteboard, spreadsheet and ModernMES

Paper or whiteboardSpreadsheetModernMES
When the number is seenWhen someone writes itThe next dayInside the shift
TargetDaily quantity divided by hoursA fixed value typed inThe running job's own rate, breaks taken out
Reason for falling behindWritten if rememberedOn a separate sheetFrom that hour's stop record
Changeover timeNot measuredWorked out by handEvery changeover, by product pair
Screen on the shop floorThe board itselfNoneBig screen view

What comes with it, and the package

The series production module is part of the Enterprise package. The same package has OEE and downtime analysis, scrap reasons, shifts, stock with a multi-level bill of materials, lot traceability, maintenance, tool and mold life, and the ERP integration. How OEE is worked out is in the OEE guide, and packages and prices are on the MES pricing page.

The 14-day trial starts on the Enterprise package and asks for no credit card. Answer "Series production to stock" or "Both" in the setup questions and the Series production module switches on by itself. Load the sample workshop and you see the board filled in before entering any data.

Frequently asked questions

Is an hour-by-hour board the same as an andon screen?

No. An andon screen shows what a machine is doing right now: running, stopped, down. An hour-by-hour board shows where you stand against the target and in which hour the gap opened. ModernMES has both. The live workshop screen shows machine status, and the Series production screen shows output against target.

My machines have no counter or PLC connection. Can I still use it?

Yes. The operator enters the quantity when starting and finishing the job on the terminal, and the board is built from those records. In that case quantities appear when the job is finished. A real hour-by-hour number takes automatic counting from the machine, which can be added later.

Who enters the target, and where?

Give the work order a quantity and an estimated time and the target is worked out by itself. If you do not enter estimated times, filling in the hourly target field on the machine form is enough.

Does the operator have to press anything extra for a changeover?

No. The changeover time is the time between finishing one job and starting a job for a different product. The operator does what they already do: finish the job and start the next.

Which package has the series production module?

The Enterprise package. Because the trial starts on Enterprise, you can try it free for 14 days.