Capacity planning Excel template (free)

Capacity planning means checking whether the work coming up for each machine group over the next few weeks fits that group's capacity. This free Excel template works out weekly capacity in hours, spreads the load of each job over the weeks and shows overloaded weeks in red on a six-week load table.

Last updated: 8 November 2026

Who is it for?

Shops that answer "when can we get this job done?" with a guess when a new order comes in. Planners who want to see ahead of time which machine group is the bottleneck, and in which week they will need overtime or outsourcing, can use it too.

Preview and download

The sample file has five machine groups and 12 jobs. The Capacity summary sheet looks like this.

ResourceWeekly capacityWeek of 26 OctWeek of 2 Nov
CNC Turning (2 machines)60.0 hours105%35%
CNC Milling (1 machine)30.0 hours74%115%
Manual machining (2 machines)56.3 hours41%0%
Welding (1 station)31.9 hours91%58%
Assembly (2 stations)67.5 hours0%59%

In the first week CNC Turning has 63.3 hours of load against 60 hours of capacity. Two jobs are planned for the same week, so the load comes out at 105% and the cell turns red. In the second week CNC Milling gets 34.5 hours, 115% of its 30 hours. Welding is yellow at 91% in the first week, which means a small hold-up could miss the due date.

Excel (.xlsx), four sheets: resources and weekly capacity, workload, a six-week load table and a detailed how-to. No email needed.

Download the template

How is capacity calculated?

Weekly capacity = Machines × Shifts per day × Shift length × Days per week × Efficiency. For the CNC Turning group with 2 machines, one shift of 7.5 hours, 5 days and 80% efficiency, weekly capacity is 2 × 1 × 7.5 × 5 × 0.80 = 60 hours.

Leave breaks out of the shift length. Efficiency is the share of time left after setups, maintenance and the stops you expect. If you are not sure, start with a value between 75% and 85% and correct it after a few weeks against what really happened. If you have downtime data, you can use the availability rate from OEE instead.

Job load = (Setup + Quantity × Time per piece) / 60, in hours. A job of 600 pieces with 45 minutes of setup and 3.2 minutes per piece adds 32.8 hours of load.

How to use it

  1. List your machine groups on the Resources sheet. Put machines that can do the same work in one group.
  2. Enter each job as a row on the Workload sheet. Pick the resource from the list, fill in the quantity, setup and time per piece, and enter the day the job will run in the Planned date column.
  3. On the Capacity summary sheet, enter the Monday of the first week. The load for six weeks comes up as a percentage.
  4. In red weeks, move the job to another week or another resource, or plan overtime or outsourcing. Have a fallback ready for yellow weeks.
  5. Leave finished jobs in the list with their dates in the past instead of deleting them. That way the load of past weeks stays on record.

What this file does not account for

The file works in weekly buckets. It compares the total load of a week with the total capacity of that week. It does not look at the order of operations, at a job waiting for its previous operation or at two jobs clashing on the same machine. That is finite capacity scheduling, and it is hard to keep up in Excel.

To see the daily plan by machine with bars, use the production schedule template.

When a spreadsheet stops being enough

A capacity plan in Excel is right as long as someone keeps the jobs and times up to date. As jobs move along, the remaining load changes and times drift from plan. The file cannot know that by itself.

In ModernMES the dashboard compares the open load of each resource group with its capacity and shows the groups that are over. The deadline check on the project page says whether capacity is enough and, if not, by how many working days it runs over. Remaining work is corrected by how far each group has drifted from plan in the past. The check assumes work can spread freely over the machines in a group. To place jobs on machines hour by hour, the Professional and Enterprise plans have a Production plan screen. See machine builders.

Frequently asked questions

How do you calculate capacity utilization?

Divide the load on a resource in a period by its capacity in the same period. If 63.3 hours of work fall on 60 hours of capacity, utilization is 105% and the work will not get done that week.

What is the difference between finite and infinite capacity planning?

Infinite capacity planning puts jobs on the date you want and checks afterwards whether capacity is enough. Finite capacity planning only places a job when the resource is free and pushes back what does not fit. This file compares load with capacity but does not move jobs by itself.

Should capacity be 100% loaded?

No. At 100% the smallest hold-up misses a due date. In a make-to-order shop, around 85% is a healthy target that leaves room for rush jobs and breakdowns.