Production schedule and calendar template for Excel (free)
This free production schedule template is a simple production plan for putting jobs on machines and days. The finish date skips weekends and your holidays, jobs that will miss their due date are flagged, every job shows as a Gantt bar, and a monthly production calendar shows what runs on each machine each day.
Last updated: 11 November 2026
Who is it for?
Small and mid-sized shops that do their weekly production plan on a whiteboard or on paper. Planners who want to see on one screen which job runs on which machine, when it starts and finishes, and whether the due dates hold can use it.
Preview and download
The sample schedule looks like this. Finish and Status are formulas. In the file, Gantt bars for 20 working days sit on the right.
| Work order | Part | Qty | Machine | Start | Working days | Finish | Due date | Status |
|---|---|---|---|---|---|---|---|---|
| WO-1042 | Flange Ø120 | 120 | CNC-01 | 2026-10-26 | 3 | 2026-10-28 | 2026-10-31 | On time |
| WO-1043 | Shaft Ø40 | 80 | Mill-01 | 2026-10-27 | 2 | 2026-10-28 | 2026-11-05 | On time |
| WO-1047 | Housing | 40 | CNC-02 | 2026-10-28 | 4 | 2026-11-02 | 2026-11-02 | On time |
| WO-1048 | Frame | 12 | Weld-01 | 2026-10-29 | 5 | 2026-11-04 | 2026-11-07 | On time |
| WO-1049 | Shaft Ø60 | 300 | CNC-01 | 2026-10-29 | 6 | 2026-11-05 | 2026-11-04 | Late |
The housing job starts on Wednesday 28 October and takes four working days. The weekend is skipped, so it finishes on Monday 2 November. The Shaft Ø60 job runs one day past its due date, so Status says "Late" and the day after the due date shows red on the bar.
Excel (.xlsx), four sheets: the schedule with a 20-working-day Gantt chart, a monthly production calendar, lists for machines and holidays, and a detailed how-to. No email needed.
Download the templateProduction calendar view
The Calendar sheet turns the same schedule into a month. Each row is a machine, each column a day, and each cell shows the work order running there that day. Weekends and holidays are grey. When two jobs land on the same machine on the same day, the cell turns red and shows +1, so double bookings are easy to spot. In the sample month the calendar looks like this:
| Machine | Mon 26 | Tue 27 | Wed 28 | Thu 29 | Fri 30 |
|---|---|---|---|---|---|
| CNC-01 | WO-1042 | WO-1042 | WO-1051 +1 | WO-1051 +1 | WO-1051 +1 |
| CNC-02 | WO-1047 | WO-1047 | WO-1047 | ||
| Mill-01 | WO-1043 | WO-1043 | |||
| Weld-01 | WO-1048 | WO-1048 |
CNC-01 has two jobs booked on 28, 29 and 30 October. Move a start date on the Schedule sheet and the calendar follows. The month is picked in one cell, so the same file works for any month.
Formulas
| Column | Formula | What it does |
|---|---|---|
| Finish | WORKDAY.INTL(Start, Days − 1, weekend, holidays) | Skips weekends and the holidays on the Lists sheet. A one-day job finishes on the day it starts. |
| Status | IF(Finish > Due date, "Late", "On time") | Flags jobs that will run past their due date. |
| Gantt days | WORKDAY.INTL(previous day, 1, weekend, holidays) | Lists the working days from the schedule start. |
| Gantt bar | Conditional formatting | The cell turns blue when the day falls between start and finish, and red when it is past the due date. |
| Calendar cell | SUMPRODUCT over Machine, Start and Finish | Counts the jobs on that machine that day and shows the work order, with +1 when there are more. |
The weekend is Saturday and Sunday by default. If you work on Saturdays, set Saturday to Working at the top of the Schedule sheet and only Sunday is skipped. Holidays go in the Holidays column of the Lists sheet, one date per row.
How to use it
- Enter the first working day of the schedule in the Schedule start cell. The 20 columns on the right are the working days from that date. If you work on Saturdays, set Saturday to Working.
- Put your machines and holidays on the Lists sheet.
- Enter a row for each job. Pick the machine from the list and fill in the start date and how many working days the job takes.
- If you see bars overlapping on the same machine, move the start dates by hand. The file does not sort out overlaps by itself.
- Open the month on the Calendar sheet. Red cells show a machine with two jobs on the same day.
- Update the schedule every morning. Do not delete finished jobs. Leave the row in place so the past schedule stays on record.
To work out the days, divide the total hours of the job by the hours the machine runs per day. A 20-hour job on one shift of 7.5 hours takes about 3 working days. To check whether the weekly load fits your capacity, use the capacity planning template.
When a spreadsheet stops being enough
A spreadsheet schedule is right at the moment it is made. When a job runs late, a machine breaks down or a rush order comes in, someone has to rework the plan. Real progress on the shop floor only reaches the file when somebody types it in.
In ModernMES each machine's job queue shows on the terminal, and the operator picks the job there or scans the job card. You can follow which job is on which machine on the live shop floor screen and the TV boards, and the project page checks against capacity whether the due date will hold. The Professional and Enterprise plans also have a Production plan screen. You drag jobs onto machines, or Place automatically lines them up by due date within working hours, and the terminal puts the machine's next planned job first. See the work order tracking guide.
Frequently asked questions
How do you make a Gantt chart in Excel?
Put the days in the top row and the start and finish date of each job in its own row. Add a conditional formatting rule to the day columns that fills a cell when its day falls between start and finish. In this file the rule is already set up.
How does the finish date skip weekends and holidays?
The WORKDAY.INTL function skips the weekend days and every date in the holiday list. It adds the duration minus one working day to the start date, because the first day of the job is a working day too. The Saturday setting makes the weekend either Saturday and Sunday or Sunday only.
What is the difference between a production schedule and a capacity plan?
A capacity plan shows whether the total load of a period fits the capacity. A production schedule decides which job runs on which machine on which day. You look at capacity first, then put the jobs on days.
What is a production calendar?
A production calendar shows, day by day, which job runs on which machine and which days are working days. In this file it is the Calendar sheet. It is built from the schedule, so you keep the plan in one place and read it either as a Gantt chart or as a month.
Related pages
- Capacity Planning Excel Template (Free)Free capacity planning template for Excel. Weekly capacity per machine group in hours, the load of each job and a six-week load table that flags overloaded weeks.
- Work Order Template for Excel & PDF (Free, Printable)Free printable work order template in Excel and as a blank PDF. Routing with planned and actual time per operation, plus a work order list that tracks due dates.
- Work Order Tracking Software for Job ShopsJob tracking for job shops: what a work order should carry, its statuses, paper and Excel vs work order tracking software, what to measure, mistakes.
- Project-Based Production Tracking for Machine BuildersEngineer-to-order tracking for machine builders: projects, parts and operations, deadline feasibility per department, and the actual hours behind each quote.