CNC job tracking spreadsheet (free Excel template)

A CNC job tracking sheet keeps the planned and actual setup time, cycle time and counts of each job side by side. In this free Excel template the planned time, the actual time and the variance between them are calculated for you. Jobs that run far off plan are marked red.

Last updated: 8 November 2026

Who is it for?

Job shops that run CNC lathes and machining centers to order. The main point is to see how well the times in your quotes match what really happens. A shop that logs setup and cycle times for a few weeks usually sees for the first time which parts it loses money on.

Preview and download

The sample rows look like this. Planned time, actual time and variance are formulas.

MachineWork orderPartQtySetup planned / actual (min)Cycle planned / actual (s)GoodScrapPlanned time (min)Actual time (min)Variance
CNC-01WO-1042Flange Ø12012045 / 5595 / 9811732352516.8%
VMC-01WO-1043Shaft Ø408030 / 28150 / 1627822302446.1%
CNC-02WO-1039Cover6040 / 70180 / 1755022202220.8%
Lathe-01WO-1045Bushing20020 / 1845 / 441960170162−4.9%

Excel (.xlsx), three sheets: CNC job tracking with program number, status and planned and actual times, machine and status lists, and a detailed how-to. No email needed.

Download the template

In the third row the cover job looks close to plan overall, but setup took 70 minutes instead of 40. The total variance is small, and only keeping setup and cycle time apart shows the gap.

Formulas

ColumnFormula
Planned time (min)Planned setup + Qty × Planned cycle / 60
Actual time (min)Actual setup + (Good + Scrap) × Actual cycle / 60
Variance(Actual time − Planned time) / Planned time

The cell turns red when a job ran more than 10% over plan and green when it finished more than 10% early. Parts and operations that keep coming up red are where the time in the quote needs a second look. How quote times are worked out is covered in our job shop quoting guide.

How to use it

  1. Put your machines on the Lists sheet.
  2. Add a row for each CNC job. Take the planned setup and cycle time from the quote or the CAM program.
  3. Set the status to Setup when the job starts and to Running while it is cutting. Fill in the actual values when it is done.
  4. Always write down the program number. When the same part comes back, it tells you which program ran and how long it took.
  5. At the end of the month, list the parts whose variance stays high and use the real time in the next quote.

When a spreadsheet stops being enough

Cycle and setup times kept in Excel are usually what the operator reports, written down after the job is done. The records end up scattered, so when the same part comes back six months later the old times are hard to find.

In ModernMES the real times build up by themselves as the operator starts and finishes each operation by scanning the job card. The typical time of each operation is worked out again every night from past jobs. When you prepare a quote, the real times of the same part, part family or resource group from the last 36 months are used. See CNC machine shops.

Frequently asked questions

How do you measure CNC cycle time?

It is the time from clamping one part to clamping the next. Measure the average over several parts, not a single one. Do not include setup in the cycle time, write it down separately.

Why keep setup time separate?

Setup is spent once per job, cycle time once per part. On small batches setup is most of the total time. If the two get mixed, both the quote and the capacity calculation come out wrong.

What does the variance percentage show?

How much longer or shorter the job took than planned. A variance above 10% says that either the time in the quote or something on the shop floor needs looking at.